Construction of Wind Tunnel Junction Underpass in Bengaluru chalega jab tak January 2027 tak!
मुख्य बातें
- •Bengaluru ke Wind Tunnel Junction underpass ki construction January 2027 tak chal sakti hai.
- •Project delay ki wajah: slow work pace aur project ki complexity.
- •GBA ne maanga hai 180 din (1 mahine ke monsoon ko chhod kar) project complete karne ke liye.
- •Heavy vehicles ke movement ko restrict kar diya gaya hai congestion avoid karne ke liye.
- •Ye junction critical hai—kai hospitals is route par hain, isliye regular ambulance movement hoti hai.
- •Project ki planning 2014 mein BBMP ne ki thi ₹135.25 crore ke cost par 16.5-km HAL Airport Road stretch ke liye.
East Bengaluru ke Wind Tunnel Junction underpass ki construction abhi tak multiple deadlines miss kar chuki hai, aur ab yeh January 2027 tak chal sakti hai, Greater Bengaluru Authority (GBA) ke ek source ke mutabik. Project shuru mein 4 mahine mein complete hone ka estimate tha, lekin slow work pace aur project ki complexity ki wajah se delay ho raha hai. GBA ne pehle hi deadline ko 7 mahine tak badha diya tha preliminary works ke baad, aur unhone 180 din ka time maanga hai (1 mahine ke monsoon ko chhod kar) project complete karne ke liye.